Berwick Township, Adams County – Beaver Creek Road Bridge Replacement

Aug 22, 2017

Tim Knoebel and Greg Hertz served as engineering representatives to Berwick Township on this project. KPI’s work involved completion of a feasibility study to assess the condition of the existing structure and to identify alternatives and related costs for its replacement. Following selection of the most cost effective alternative KPI provided survey and design services including completion of bid documents. We also provided construction management services including inspection, review of payment requests and related work.